- No new struvite in 60+ days
- Downtime 3 days to 6 hours
- $16–40k a year avoided

Guelph WWTP: Belt Press Downtime Cut From 3 Days to 6 Hours
- KEY RESULTS
Summary
At Guelph WWTP, a HydroFLOW® i160 trial on the belt press feed recorded no new struvite build-up over more than 60 days of continuous running. Maintenance downtime fell from three days to six hours, and the outside pressure-wash contractors, previously $16,000 to $40,000 a year, were no longer needed. Struvite problems in the belt press and centrate discharge were virtually eliminated.
Belt press struvite control at Guelph WWTP
Belt press struvite control was costing Guelph Wastewater Treatment Plant days of downtime. The plant serves the City of Guelph and the surrounding Guelph and Eramosa townships in Ontario and dewaters its sludge on Ashbrook belt presses, where hard struvite built up on rollers, drains, bearings, pistons and drums, and the six-inch centrate discharge piping could block completely. One HydroFLOW® i160 was installed on the steel feed pipe upstream of a belt press for a 60-day trial. No new struvite build-up was reported over more than 60 days of continuous running, maintenance downtime fell from three days to six hours, and outside pressure-wash contractors were no longer needed.
Project Details

The Challenges
- Belt press struvite control was needed to cut costly, labour-intensive maintenance
- Six-inch centrate discharge piping could block completely
- Deposits built up on rollers, drains, bearings, pistons and drums
- Removing hard deposits meant extensive cleaning and prolonged shutdowns
- Outside pressure-wash contractors cost $16,000 to $40,000 a year
The Solution
- Unit installed: one HydroFLOW® i160
- Installation point: steel feed pipe upstream of the Ashbrook belt press inlet
- Pipe: 150 mm (6 in) OD steel
- Trial: 60 days of continuous operation
For belt press struvite control, the i160 was fitted to the steel feed pipe just upstream of the press inlet, so the sludge was treated before it reached the press and the centrate discharge system. The press then ran continuously for 60 days, and its drains and drum openings were inspected and photographed at the end.
Testimonial
“After 60 days of continuous operation the result was significantly positive, the build-up of Struvite was eliminated”
— Rony George, Plant Maintenance Supervisor
Key Outcomes
No new struvite in 60+ days
$16–40k a year contractors avoided
92% less maintenance downtime
Discharge blockages virtually ended
Independent Verification
All results in this study were measured and verified by third-party facilities managers and technical staff.
Ready to see more?
Other Case Studies
Manufacturing
Guangdong PCB Factory: RO Output Doubled From 12 to 24 t/h
HydroFLOW® helped double RO output from 12 to 24 tonnes an hour in 15 days at a Guangdong PCB factory, with permeate conductivity down about two-thirds.
- RO output doubled in 15 days
- ~67% lower permeate conductivity
- 4 more
- units ordered
Waste Water
Woodward Avenue WWTP: Centrifuge Ports Kept Clear of Struvite
A HydroFLOW® i160 kept centrifuge ports and centrate pipework clear of struvite at Hamilton’s Woodward Avenue WWTP, with payback under a year.
- No port or pipe blockages
- $50k+ projected yearly saving
- Payback under 1 year
Waste Water
HERA Bologna: Sludge Shredder Ran 65 Days Without Stopping
A HydroFLOW® i160 kept HERA’s Bologna sludge shredder running for at least 65 days without a struvite stoppage, against 20 to 30 days before.
- 65 days
- without interruption
- 3x
- longer maintenance intervals
- Trial units bought