- ~70% slower flow decline
- 4,400
- L/h held after 4 weeks
- Both units purchased

Eindhoven Coatings Factory: RO Flow Decline Slowed ~70%
- KEY RESULTS
Summary
HydroFLOW® helped stabilise RO performance at an Eindhoven coatings factory, with trend analysis showing an approximately 70% slower decline in permeate flow during the initial trial. Permeate flow was still 4,400 L/h after four weeks, where it had previously fallen to 3,500 L/h in about three months. The positive early results led the customer to buy both units.
RO membrane scaling at an Eindhoven coatings factory
RO membrane scaling was cutting permeate flow at a coatings factory in Eindhoven, Netherlands, which uses reverse osmosis to make demineralised water for its production process. RO system 1 runs at 85% recovery with 2.0 m³/h of concentrate recirculated, and after membrane cleaning its permeate flow fell to 3,500 L/h in about three months. HydroFLOW® P100 and HS40 units were fitted to RO system 1, with the P100 on the RO 1 feed line, and performance was monitored following membrane cleaning. The decline in permeate flow was then around 70% slower, flow was still 4,400 L/h after four weeks, and the customer bought both units.
Project Details

The Challenge
- RO membrane scaling caused rapid permeate-flow loss between cleans
- Permeate flow fell to 3,500 L/h in about three months
- The RO system ran at 85% recovery
- 2.0 m³/h of concentrate was recirculated

The Solution
- Units installed: one HydroFLOW® P100 and one HS40
- Installation point: P100 on the RO 1 feed line
- System: RO system 1, making demineralised water at 85% recovery
- Concentrate recirculation: 2.0 m³/h
To see whether RO membrane scaling could be slowed, the HydroFLOW® units were fitted to RO system 1 and permeate flow was monitored following membrane cleaning. The flow trend with the units in place was then compared with the earlier decline without them, using linear trend analysis.
Key Outcomes
~70% slower flow decline
85% recovery RO
4,400 L/h after 4 weeks
Both units purchased
Independent Verification
All results in this study were measured and verified by third-party facilities managers and technical staff.
Ready to see more?
Other Case Studies
Manufacturing
Guangdong PCB Factory: RO Output Doubled From 12 to 24 t/h
HydroFLOW® helped double RO output from 12 to 24 tonnes an hour in 15 days at a Guangdong PCB factory, with permeate conductivity down about two-thirds.
- RO output doubled in 15 days
- ~67% lower permeate conductivity
- 4 more
- units ordered
Manufacturing
Ontario Steel Mill: Spray Line Clogging Cut From 65% to 10%
One HydroFLOW® i100 cut supply-line clogging on a steel mill's galvanising spray bars from 65% to 10%, with no blockages reported for a year.
- 65%
- to 10% line clogging
- 1 year
- without blockages
- 3-month calculated payback
Manufacturing
Boise Paper: Treated Shower Nozzles Clear After 11 Weeks
At Boise Paper's Wallula bleach plant, shower nozzles treated by a HydroFLOW® Custom 8” stayed substantially clearer than an untreated unit after 11 weeks.
- 11
- weeks, treated nozzles clear
- 30 ft
- of pipework treated
- No hydroblasting required
