Aerial view of the PepsiCo Walkers crisp factory in Leicester, HydroFLOW spray nozzle scale treatment case study

PepsiCo Walkers: 24 Weeks of Clear 200-Micron Nozzles

  • KEY RESULTS
    24 weeks
    without cleaning
    Estimated 95% lower cleaning cost
    147 hours
    of downtime avoided

Summary

Nozzles that needed an acid-bath clean every week stayed clear for 24 weeks, and the three hours of stopped line that came with each clean went with them. The report estimated a 95% annual reduction in nozzle-cleaning costs.

Spray nozzle scale blockage on the crisp line

Spray nozzle scale blockage was stopping the line every week at the UK’s largest crisp factory. Four sets of 200 micron nozzles on the cold-water spray bars were blocking as pressure dropped at the outlets, and each acid-bath clean took three hours with the line down. One HydroFLOW® i45 was fitted after the pumps on the two flexible feed pipes, treating all four nozzle sets. The nozzles stayed clear for 24 weeks and the weekly acid soak stopped. Around 147 hours of annual production downtime and about 196 litres of acid solution a year were avoided, and the report estimated a 95% annual reduction in nozzle-cleaning costs.

The Challenge

  • Spray nozzle scale blockage stopped the line every week
  • 200 micron outlets were highly vulnerable to scale blockage
  • Pressure reduction at the outlets encouraged scale formation
  • Each acid-bath cleaning took three hours with the line stopped
  • Cleaning created downtime, labour and chemical costs

The Solution

  • Unit installed: one HydroFLOW® i45
  • Installation point: after the pumps, on two flexible plastic feed pipes
  • System: four sets of 200 micron nozzles on the cold-water spray bars
  • Previous treatment: weekly three-hour acid-bath clean

The spray nozzle scale blockage was addressed with one unit fitted after the pumps, where it could treat both flexible feed pipes before the water reached the spray bars. Nozzles that had blocked weekly stayed clear for 24 weeks, so the weekly three-hour acid soak and the production stoppage that went with it were no longer needed.

Key Outcomes

  • Nozzles previously cleaned weekly stayed clear for 24 weeks

  • Around 147 hours of annual production downtime avoided

  • Estimated 95% annual reduction in nozzle cleaning costs

  • Roughly 196 litres of acid solution saved a year, across 49 avoided cleans

Independent Verification

All results in this study were measured and verified by third-party facilities managers and technical staff.

Ready to see more?

Other Case Studies

  • Jars of tomato sauce moving along a stainless steel food packaging lineFood Industry

    Puglia Food Plant: No Marks on Washed Jars in 7 Days

    One HydroFLOW® i45 ended mineral marks on washed jars within 7 days at a Puglia food plant, stopped dispersant dosing and cut surfactant by 80%.

    7 days
    to mark-free jars
    80%
    less surfactant
    9-month reported payback
  • Food processing factory – microbial reduction with the i45, ItalyFood Industry

    Italy Food Plant: 99.95% E. coli Cut in 21 Hours

    Cesarin S.p.A. cut microbial load in fermented pepper concentrate by up to 99.95% with a HydroFLOW® i45 on a 300L pilot recirculation system.

    99.95%
    E. coli reduction
    99.6%
    CMT reduction
    21 hours
    treatment time
  • Green apples in a produce wash flume at an apple packing facility, US Northwest, HydroFLOW water treatmentFood Industry

    US Apple Packer: 14 Extra Years From Ageing Heaters

    A US apple packing facility cut industrial water heater limescale by over 70% in three months and kept three ageing heaters running for another 14 years.

    Over 70% less scale in 3 months
    14 extra
    years of heater life
    6 units
    over 15 years